June 2019-April 2020
In order to address key limiting factors for salmonids, this restoration improved and enhanced fish and wildlife habitat along a quarter of mile section of North Scappoose Creek. Improvements to the physical habitat quality and complexity included installing large wood within the stream bank, laying back a short section of the stream bank, and adding a significant amount of native riparian vegetation.
Project Goals
The project goals were to:
- Enhance fish habitat and in-stream channel complexity
- Increase native vegetation and diversity along riparian corridor to reduce streambank erosion, increase stream shading, and support future large wood availability
Location
Project activities occurred primarily on the left (north) bank of North Scappoose Creek between Hwy 30 and Scappoose-Vernonia Road.
Timeline
- Project construction: June 2019 – September 2019
- Riparian planting: October 2019 – April 2020
Project Map
More Information
For more information contact the Scappoose Bay Watershed Council at 503-397-7904 or email: info@scappoosebay-wc.org.